UPGRADE PANEL DCB PLC FOR 1 PANEL AND SCADA FOR 3 PANEL USING S7-300

Project Purpose : Upgrade panel DCB PLC for 1 panel and Scada for 3 panel using S7-300 Challenge : Upgrade conventional panels to automation. Solution : To meet their needs we use SIMATIC S7-300 CPU 315-2 PN/DP, and all processes run smoothly

Panel Inverter 5,5 kW

Project Purpose : Procurement of 5.5 kW inverter panels Challenge : - Solution : To meet the needs of PT.T panels we use SINAMICS V20, and all processes run smoothly

ELECTRICAL GRINDING MILL

Project Purpose : Electrical Grinding Mill Challenge : PT A carried out contract work with PT B located in the Bandung area to carry out work on making a new plant using a GRINDING MILL machine from Germany where we are given the scope of electricity by procuring MCC panels

MIGRATION PROGRAM AND COMMISIONING INVERTER

Project Purpose : Carried out program transfer and inverter commissioning for the process of checking the standardization of tires at BRIN Challenge : The inverter on the BRIN has a short circuit resulting in standard checks for tires not operating and braking resistors not working Solution : Thanks to  Sinamics

PLC PANEL FOR TEMPERATURE MONITORING

  Project Purpose : Requires temperature monitoring in buildings at PLTU, needs for I/O and PLC control on the DCS that they had Challenge : The PLTU has a control panel with the main PLC S7-1200, it needs a program and the right accuracy to measure temperature in a relatively

VSD CASCADE WITH PLC

  Project Purpose : Installing and commissioning to start 4 motors using vsd with PLC control Challenge : Several motors need to be started and require a VSD with the need for a program on the main PLC S7-1200 with a fairly short time Solution : Thanks to the Siemens

PLC Programming & HMI Palletizer Packing Plant

  Project Purpose : To expand palletizer machines and buffer warehouses at PT. A Plant, it is necessary to have an additional IO on PLC control and the addition of a SCADA screen for the automation process Challenge : PT A has a control panel with a main PLC S7

PT. A Commissioning Local Support Engineer

  Project Purpose : To assist the Commissioning process of conveyor panels and transfer cars at PT A Kediri Warehouse. Challenge : PT. B has control panels for conveyor and transfer car systems which use the Siemens brand as the main control supported by other brands. But on the other

Transfer Switch For Transformer Backup

  Project Purpose : The Transfer Switch for Transformer Back Up aims to enable the spare transformer in the onshore MCC room to be activated quickly when the main transformer experiences Challenge : PT. A has Transformer 01 and Transformer 02, currently only Transformer-01 is active and used in electricity

EPC Electrical CP1 Revitalization

  Project Purpose : Project lumpsum for Construction of Coal Handling Facilities and Conveyor system Challenge : PT. A plans to gradually increase coal production to reach 36-40 MTPA. To support this production goal, it is necessary to build Coal Handling Facilities and Conveyor system infrastructure for operations and maintenance